Power. Fiber. Water. All Private. The Hyperscale Site That Shouldn't Exist.
17,571 deeded acres. 3+ GW solar. OPGW fiber on the gen-tie. Sub-20ms to Silicon Valley. 3,226 AF/yr of senior water rights. Zero federal land. Zero NEPA. County permits only.
Two Private Ranches. Two Grid Paths. Zero Federal Risk.
17,571 deeded acres across two independent grid pathways — 100% fee-simple ownership, zero BLM permitting on either site
Two Independent Grid Pathways
~3 miles to 345kV Tracy-Valmy (Clear Creek) and ~22 miles to Robinson Summit 500kV (Butte Valley) — independently verified against OSM and HIFLD federal data
Dual Transmission Pathways
Two independent grid connections eliminate single-point-of-failure risk and provide access to Nevada's full transmission network.
- Clear Creek (Lead Asset): ~3 mi to NV Energy 345kV Tracy-Valmy corridor — flat desert gen-tie, no mountain crossings. Connects via Tracy Sub to Fort Churchill and Greenlink West.
- Butte Valley: ~22 mi to Robinson Summit 500kV convergence hub. ON Line (600MW, operational since 2014) + Greenlink North (525kV, ~240 mi, 2026–2028) + Cross-Tie (1,500MW, 500kV, ~214 mi to Utah, 2027–2028) all meet at Robinson Summit
- Cross-Verified: Distances confirmed against OSM and HIFLD federal transmission data (DHS/DOE, 40-ft avg. offset)
- Market Access: CAISO, Pacific Northwest, and Southwest corridors via both pathways
- Queue Window: OASIS interconnection study window opens June–July 2026
* Most competitors face 15–40 mi gen-ties across federal land
Dual 345 kV + 500 kV grid pathways — ready for hyperscale interconnection.
Request Data Room AccessA Conceptual Geothermal Layer on the Exact Same Land.
Clear Creek sits on the eastern margin of the Battle Mountain–Eureka trend — one of the most productive geothermal corridors in the continental U.S. The same 345 kV Tracy–Valmy gen-tie and the same NRS 534A private-surface regime that make it a Tier-1 solar platform would support a conceptual firm baseload layer on the same 14-parcel footprint.
Jersey Valley — Same County. Same Structure. Same Permitting. Operating Since 2010.
Ormat's Jersey Valley binary plant is the single most directly relevant analog in Nevada: same Pershing County, same extensional structural setting, same NRS 534A private-surface framework, same binary-cycle economics.
Analog economics alone do not establish resource presence at Clear Creek. Temperature-gradient drilling and magnetotelluric survey work are required — exactly what the stage-gated program below is structured to deliver.
The Template Already Exists
Three precedent hyperscaler × geothermal transactions in the last 24 months — two of them in the Basin and Range province where Clear Creek operates.
Nevada + Utah
East of Rockies
Nevada
Utah
Kenya
Stage-Gated 2026–2031 Pathway
Capital released stage by stage against technical gates. No material well-field spend until the resource is temperature- and flow-validated.
Heat-flow, MT/gravity, structural mapping.
3–6 slim holes to 500–1,500 ft.
2–3 full-depth wells to 6–10k ft.
Doublets, binary/flash plant, grid tie.
Contractual vehicle: Nevada Clean Transition Tariff, approved by PUCN on May 13, 2025 — a direct bilateral pathway for large-load customers to procure incremental clean generation. Conceptual feasibility based on regional heat-flow trends and producing analog fields. No site-specific temperature-gradient drilling, MT survey, or exploration wells have been completed at Clear Creek to date. All figures are ranges, subject to confirmation through the stage-gated program above. Nothing here constitutes a resource report under SEC or SPE standards.
The full Clear Creek Geothermal Feasibility analysis is available in the confidential data room.
Request Full Feasibility Analysis$850M+ Platform Value Identified Across Two Sites.
The full financial model — NPV ranges, phase-by-phase capex, firm-power premium analysis, and ITC stacking — is available in the confidential data room. Here is the headline structure.
Full financial model, feasibility analyses, and legal documentation available under NDA.
Fiber-Ready Data Center Campus
OPGW fiber on the same gen-tie that delivers power — sub-20ms to Silicon Valley — 3,226 AF/yr water for cooling — county permits only
Optical Ground Wire on NV Energy 345kV Tracy-Valmy corridor. Most efficient co-location architecture available.
400G DEAN architecture, ~800 mi, BLM-approved, under construction through Pershing County. Open-access dark fiber.
Ultra-low latency to Silicon Valley, Sacramento, and Western U.S. cloud hubs. Carrier diversity via Zayo + Lumen (Level 3) on I-80 corridor.
Solar uses only ~20 AF/yr per GW. Massive surplus for DC evaporative cooling + ranch operations.
Evaporative cooling advantage from 3,226 AF/yr senior water rights. Pre-1940s priority — no curtailment risk.
Buried fiber on private land. County permitting only. Direct connection to OPGW and Zayo backbone.
Zero federal involvement. Zero NEPA. County SUP + local permitting for speed-to-market.
Two Data Center Campuses. Different Strengths. One Platform.
Each site fills the other's structural gap. Zero cross-site dependency. A hyperscaler can fund Phase 1 work on both in parallel.
- ✓ 3.26 mi to 345 kV + OPGW fiber
- ✓ $378K–$430K fiber lateral cost
- ✓ 3–6 months to fiber-ready
- ✓ Zayo I-80 backbone ~30 mi
- ✓ Sub-20ms to Silicon Valley
- ✓ 2,569 AF/yr senior water rights
- ✓ 50–100 MW firm 24/7 geothermal
- ✓ County permitting only (NRS 534A)
- ✓ 500 kV Robinson Summit hub — 4 outbound paths
- ✓ Cold-climate PUE advantage ($40–75M savings over 20 yr)
- ✓ 6,000–6,500 ft elevation — natural cooling
- ✓ Top-decile 6.0+ kWh/m²/day solar irradiance
- ✓ 100–200 MW Phase 1 solar + BESS
- ✓ 657 AF/yr senior water rights
- ✓ Flat terrain, road access — purpose-built for hyperscaler infrastructure
- ✓ County permitting only
Why Two Sites Beat One
Helios X vs. Typical BLM Sites
Every factor that delays federal projects is eliminated here
| Factor | Helios X (Private) | Typical BLM Site |
|---|---|---|
| Land Control | FEE-SIMPLE | Right-of-Way lease |
| NEPA Required | NO | YES (EIS/EA) |
| Federal Permitting | NONE | 18-36+ months |
| Development Certainty | HIGH | VARIABLE |
| Time to COD | 2-3× FASTER | Extended |
| Permitting Cost | 30-50% LOWER | Higher |
| Tax Equity Risk | LOWER | HIGHER |
| Water Rights | PRE-1940s SENIOR | Often contested |
| Agrivoltaics Compatible | PROVEN OPS | Limited/uncertain |
| Fiber Optic Access | OPGW ON GEN-TIE | None (typical) |
| Data Center Co-Location | CAMPUS READY (9/10) | Not applicable |
Proven Agrivoltaic Operations
40 years of active ranching — 1,650 cattle + 9,000 sheep — ready for dual-use solar integration
Established Operations
40-year family ranching history with proven grazing management across 1.49 million controlled acres — active operations on both Clear Creek and Butte Valley ranches
Senior Water Rights
Pre-1940s priority rights with 3,226 AF/year permitted — no disputes, year-round availability
Dual-Use Ready
Infrastructure in place for seamless solar-grazing integration — aligned with Silicon Ranch model
Helios X vs. Silicon Ranch Snipesville (Flagship Site)
Helios X
Snipesville
Helios X Livestock
Snipesville
Up to 50% ITC + Critical Safe Harbor Deadline
IRA credit stacking on 3+ GW private-land platform — construction must begin by July 4, 2026
ITC Credit Stack
1 Prevailing wages + apprenticeship requirements apply.
2 Subject to fossil fuel employment (FFE) qualification at construction start.
3 Subject to domestic equipment availability at economic price.
OBBBA Safe Harbor Deadline
Combined Platform
Behind-the-Meter Power
Energy Community Certified
ITC eligibility subject to prevailing wage, apprenticeship, and equipment sourcing requirements. Subject to detailed feasibility study, interconnection studies, and tax counsel review.
Roche Ranches — 3rd Generation
Our family has operated one of the largest ranching enterprises in the Intermountain West for over 40 years. We're not looking for a quick lease check — we want to build something that lasts, integrating renewable energy with our agricultural heritage.
Helios X represents our commitment to the future: clean energy production that complements and enhances our ranching operations, creating value for generations to come.
See It. Evaluate It. Build It.
Walk 17,571 acres of private land. Direct access to the landowner.
Contact Helios X
Confidential data room access requires NDA execution. All materials prepared with institutional-grade legal and financial counsel.